Development of a turnkey equipment complex for a salt effluent concentration section.
WORKS
Reagent treatment of water circulation cycles of water supply systems:
Development of technology
Supply of equipment for wastewater treatment with the production of 120 m3/h of purified water, but reuse and concentration of 10 m³/h of concentrate for disposal
Engineering with a set of technical documentation. An extended warranty for a period of 3 years is provided.
Technology
Basic engineering
Detailed engineering
Equipment supply
Reagent supply
Installation supervision
Commissioning
Personnel training
PROJECT 2021-2025
Salt effluent concentration section.
Development of a turnkey equipment complex for a salt effluent concentration section.
WORKS
Reagent treatment of water circulation cycles of water supply systems:
Preparation of the site for equipment installation
Supervision of installation and adjustment of equipment
Supply of reagents
Warranty testing
Personnel training.
An extended warranty period of 3 years is provided.
Technology
Basic engineering
Detailed engineering
Supply of equipment
Supply of reagents
Supervision of installation Commissioning
Personnel training
PROJECT 2021-2024
Casting and rolling complex section.
Reconstruction of recycling water supply facilities of the LPK.
WORKS
Survey of the existing recycling water supply system of the LPK
Development of solutions for changing the technological process of the existing technology